Work Not Permissible in VB-GRAM-G
Work Type Configuration A ๐Ÿ“ SIDHI
-
Score / 10
Total Started
395
All started works
Completed
33
Financially closed
Phys. Completed
242
Physical closure pending
Sanctioned
โ‚น21.17 Cr
Total budget
Booked (53.2%)
โ‚น11.27 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
69.6%
275 of 395 works done (69.6%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
53.2%
โ‚น11.27 Cr booked of โ‚น21.17 Cr sanctioned
Work Not Permissible in VB-GRAM-G โ€” Daily Progress Trend
Completed works over last 30 days
Work Not Permissible in VB-GRAM-G โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
120 works
โ—‰
Physically Completed
242 works
โœ“
Completed
33 works
Status Summary
๐Ÿ“Š
Total works started: 395
Snapshot: 2026-07-02
Active
โœ…
Completion status: 69.6%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 53.2%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท SIDHI ยท Work Not Permissible in VB-GRAM-G ยท 2026-07-02
5 blocks
#
1 SIHAWAL 119 9 71 39 1 15 67.2% 51.5% โ‚น2.84 Cr
2 SIDHI 101 5 67 29 3 14 71.3% 54.8% โ‚น2.62 Cr
3 RAMPUR NAIKIN 90 11 46 33 6 12 63.3% 53.0% โ‚น2.40 Cr
4 MAJHAULI 55 6 33 16 8 13 70.9% 49.7% โ‚น1.95 Cr
5 KUSMI 30 2 25 3 2 1 90.0% 60.2% โ‚น1.46 Cr