โœ• Clear Filters
๐Ÿงบ
Dug Well Recharge
Work Type Configuration A ๐Ÿ“ SINGRAULI
-
Score / 10
Total Started
1,116
All started works
Completed
638
Financially closed
Phys. Completed
457
Physical closure pending
Sanctioned
โ‚น2.88 Cr
Total budget
Booked (59.0%)
โ‚น1.70 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
98.1%
1,095 of 1,116 works done (98.1%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
59.0%
โ‚น1.70 Cr booked of โ‚น2.88 Cr sanctioned
Dug Well Recharge โ€” Daily Progress Trend
Completed works over last 30 days
Dug Well Recharge โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
21 works
โ—‰
Physically Completed
457 works
โœ“
Completed
638 works
Status Summary
๐Ÿ“Š
Total works started: 1,116
Snapshot: 2026-07-02
Active
โœ…
Completion status: 98.1%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 59.0%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท SINGRAULI ยท Dug Well Recharge ยท 2026-07-02
3 blocks
#
1 CHITRANGI 391 233 145 13 43 55 96.7% 58.1% โ‚น0.59 Cr
2 WAIDHAN 365 86 273 6 5 24 98.4% 68.6% โ‚น0.64 Cr
3 DEOSAR 360 319 39 2 28 37 99.4% 50.6% โ‚น0.47 Cr