Farm Pond
Work Type Configuration A ๐Ÿ“ CHHINDWARA
-
Score / 10
Total Started
2,432
All started works
Completed
913
Financially closed
Phys. Completed
1,210
Physical closure pending
Sanctioned
โ‚น59.07 Cr
Total budget
Booked (75.2%)
โ‚น44.39 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
87.3%
2,123 of 2,432 works done (87.3%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
75.2%
โ‚น44.39 Cr booked of โ‚น59.07 Cr sanctioned
Farm Pond โ€” Daily Progress Trend
Completed works over last 30 days
Farm Pond โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
309 works
โ—‰
Physically Completed
1,210 works
โœ“
Completed
913 works
Status Summary
๐Ÿ“Š
Total works started: 2,432
Snapshot: 2026-07-02
Active
โœ…
Completion status: 87.3%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 75.2%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท CHHINDWARA ยท Farm Pond ยท 2026-07-02
11 blocks
#
1 JAMAI 470 282 112 76 โ€” 2 83.8% 82.3% โ‚น8.61 Cr
2 HARAI 396 161 153 82 โ€” โ€” 79.3% 75.1% โ‚น5.69 Cr
3 AMARWARA 347 134 203 10 17 6 97.1% 65.9% โ‚น6.53 Cr
4 TAMIA 269 117 109 43 โ€” โ€” 84.0% 72.8% โ‚น8.11 Cr
5 SAUSAR 185 40 102 43 2 โ€” 76.8% 73.5% โ‚น2.31 Cr
6 PARASIA 176 39 116 21 โ€” 6 88.1% 76.9% โ‚น3.85 Cr
7 BICHHUA 137 3 128 6 โ€” 7 95.6% 80.4% โ‚น2.03 Cr
8 PANDHURNA 135 79 44 12 โ€” 1 91.1% 62.7% โ‚น1.50 Cr
9 MOHKHED 126 12 104 10 โ€” 5 92.1% 87.7% โ‚น1.91 Cr
10 CHAURAI 98 7 88 3 โ€” 1 96.9% 89.5% โ‚น2.80 Cr
11 CHHINDWARA 93 39 51 3 1 4 96.8% 65.3% โ‚น1.05 Cr