Farm Pond
Work Type Configuration A ๐Ÿ“ SEONI
-
Score / 10
Total Started
3,076
All started works
Completed
1,969
Financially closed
Phys. Completed
937
Physical closure pending
Sanctioned
โ‚น80.58 Cr
Total budget
Booked (63.5%)
โ‚น51.18 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
94.5%
2,906 of 3,076 works done (94.5%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
63.5%
โ‚น51.18 Cr booked of โ‚น80.58 Cr sanctioned
Farm Pond โ€” Daily Progress Trend
Completed works over last 30 days
Farm Pond โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
170 works
โ—‰
Physically Completed
937 works
โœ“
Completed
1,969 works
Status Summary
๐Ÿ“Š
Total works started: 3,076
Snapshot: 2026-07-02
Active
โœ…
Completion status: 94.5%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 63.5%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท SEONI ยท Farm Pond ยท 2026-07-02
8 blocks
#
1 LAKHNADON 856 694 113 49 96 126 94.3% 55.3% โ‚น9.30 Cr
2 KEOLARI 505 413 63 29 9 1 94.3% 69.0% โ‚น10.26 Cr
3 KAHNAPAS(GHANSAUR) 424 235 177 12 66 75 97.2% 54.9% โ‚น5.35 Cr
4 BARGHAT 418 247 159 12 5 23 97.1% 72.7% โ‚น8.63 Cr
5 DHANAURA 312 186 107 19 28 62 93.9% 57.9% โ‚น4.39 Cr
6 KURAI 248 39 176 33 2 12 86.7% 67.6% โ‚น6.68 Cr
7 CHHAPARA 202 101 91 10 2 8 95.0% 64.1% โ‚น4.28 Cr
8 SEONI 111 54 51 6 โ€” 10 94.6% 72.6% โ‚น2.28 Cr