Farm Pond
Work Type Configuration A ๐Ÿ“ SHAHDOL
-
Score / 10
Total Started
2,662
All started works
Completed
775
Financially closed
Phys. Completed
1,503
Physical closure pending
Sanctioned
โ‚น72.06 Cr
Total budget
Booked (65.2%)
โ‚น47.01 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
85.6%
2,278 of 2,662 works done (85.6%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
65.2%
โ‚น47.01 Cr booked of โ‚น72.06 Cr sanctioned
Farm Pond โ€” Daily Progress Trend
Completed works over last 30 days
Farm Pond โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
384 works
โ—‰
Physically Completed
1,503 works
โœ“
Completed
775 works
Status Summary
๐Ÿ“Š
Total works started: 2,662
Snapshot: 2026-07-02
Active
โœ…
Completion status: 85.6%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 65.2%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท SHAHDOL ยท Farm Pond ยท 2026-07-02
5 blocks
#
1 JAISINGHNAGAR 833 225 452 156 7 99 81.3% 60.8% โ‚น13.36 Cr
2 BURHAR 685 93 517 75 5 83 89.1% 74.8% โ‚น17.79 Cr
3 GOHPARU 534 244 261 29 8 69 94.6% 70.1% โ‚น8.31 Cr
4 SOHAGPUR 347 105 160 82 11 161 76.4% 55.5% โ‚น4.44 Cr
5 BEOHARI 263 108 113 42 11 88 84.0% 48.5% โ‚น3.12 Cr