Repair & Maintenance (Water Structures)
Work Type Configuration A ๐Ÿ“ ASHOK NAGAR
-
Score / 10
Total Started
33
All started works
Completed
5
Financially closed
Phys. Completed
28
Physical closure pending
Sanctioned
โ‚น2.43 Cr
Total budget
Booked (82.7%)
โ‚น2.01 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
100.0%
33 of 33 works done (100.0%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
82.7%
โ‚น2.01 Cr booked of โ‚น2.43 Cr sanctioned
Repair & Maintenance (Water Structures) โ€” Daily Progress Trend
Completed works over last 30 days
Repair & Maintenance (Water Structures) โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
0 works
โ—‰
Physically Completed
28 works
โœ“
Completed
5 works
Status Summary
๐Ÿ“Š
Total works started: 33
Snapshot: 2026-07-02
Active
โœ…
Completion status: 100.0%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 82.7%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท ASHOK NAGAR ยท Repair & Maintenance (Water Structures) ยท 2026-07-02
4 blocks
#
1 CHANDERI 14 1 13 0 โ€” โ€” 100.0% 78.2% โ‚น0.76 Cr
2 ASHOKNAGAR 8 2 6 0 โ€” โ€” 100.0% 90.5% โ‚น0.61 Cr
3 MUNGAOLI 6 0 6 0 โ€” โ€” 100.0% 82.2% โ‚น0.39 Cr
4 ISAGARH 5 2 3 0 โ€” โ€” 100.0% 80.7% โ‚น0.25 Cr