Total Started
118
All started works
Completed
48
Financially closed
Phys. Completed
65
Physical closure pending
Sanctioned
โ‚น8.22 Cr
Total budget
Booked (75.3%)
โ‚น6.19 Cr
Wages + Material
Work Completion Progress
Completed + Physically Completed counted as done ยท Ongoing does NOT count
95.8%
113 of 118 works done (95.8%)
Booked Expenditure Progress
Booked amount as percentage of sanctioned amount
75.3%
โ‚น6.19 Cr booked of โ‚น8.22 Cr sanctioned
Repair & Maintenance (Water Structures) โ€” Daily Progress Trend
Completed works over last 30 days
Repair & Maintenance (Water Structures) โ€” Financial Progress
Booked amount over last 30 days
Work Status Distribution ยท 2026-07-02
โœ“
Ongoing
5 works
โ—‰
Physically Completed
65 works
โœ“
Completed
48 works
Status Summary
๐Ÿ“Š
Total works started: 118
Snapshot: 2026-07-02
Active
โœ…
Completion status: 95.8%
Completed + Physically Completed
Progress
๐Ÿ’ฐ
Budget execution: 75.3%
Booked vs Sanctioned Amount
Financial
Block-wise Breakdown ยท SEONI ยท Repair & Maintenance (Water Structures) ยท 2026-07-02
8 blocks
#
1 LAKHNADON 39 19 18 2 โ€” โ€” 94.9% 73.9% โ‚น1.54 Cr
2 SEONI 18 11 5 2 โ€” โ€” 88.9% 69.0% โ‚น0.76 Cr
3 DHANAURA 18 2 16 0 โ€” โ€” 100.0% 79.4% โ‚น1.56 Cr
4 KURAI 14 4 9 1 โ€” โ€” 92.9% 71.7% โ‚น0.57 Cr
5 KEOLARI 11 4 7 0 โ€” โ€” 100.0% 85.6% โ‚น0.69 Cr
6 BARGHAT 8 5 3 0 โ€” โ€” 100.0% 76.2% โ‚น0.47 Cr
7 KAHNAPAS(GHANSAUR) 5 1 4 0 โ€” โ€” 100.0% 71.3% โ‚น0.29 Cr
8 CHHAPARA 5 2 3 0 โ€” โ€” 100.0% 69.9% โ‚น0.31 Cr